New construction Children’s and youth centre Pastorius­straße

Project description

The facility is intended to be used jointly by children and young people of the district. The new building also serves as a meeting place for the citizens of the districts, who can attend events there.
The free-standing new youth centre with a gross floor area of 724 m² and a usable space of 447 m² has two to three storeys and a coherent polygonal design with additional rooms and outdoor facilities for sports use.

Location

The new building is located in the Zabo district on Pastoriusstraße 49. It is located in the southern part of the site and shields the noise generated on the open spaces to the north from the adjacent flats to the south. Due to the chosen location and the screening effect of the children’s and youth centre, it was not necessary to erect a noise barrier as planned in the development plan.

Energy standard

The building, which complies with the EnEV standard (energy requirements for new buildings), is connected to the public district heating network and has underfloor heating. The ventilation equipment includes two individual units with heat recovery, which, among other things, mechanically ventilate the sports hall as well as the foyer and event room with potential noise levels.
The interior WCs have exhaust fans with after-flow, the kitchen a wall ventilator with heat recovery. The other rooms are naturally ventilated by window ventilation.
The building has a burglar alarm system. Drainage is provided within the site in a separate system (separate pipes for the drainage of wastewater and rainwater), outside in the existing combined system. Hot water is provided by external water heaters. The sanitary facilities are adapted to the operational requirements.

Special features

In addition to providing the usual services of a children’s and youth centre, the concept of the KJH Pastoriusstraße includes the basic concept of sports facilities developed especially for the centre. Inside the building, for example, a sports hall and a group room that can be used as a gymnastics room allow for sports activities.
Particular emphasis was placed on creating an open view that presents the young people’s sporting activities as openly and invitingly as possible to the outside and allows for flowing spatial relationships on the inside.

Facts

Gross floor area

        724 m²

Usable area

        447 m²

Usable area, sports grounds   

        177 m²

Outdoor area

Approx. 1,054 m²

Parking spaces

3

Total costs

€2.85 million

Start of construction

2017

Completion of construction

October 2019

Architects

stm architekten PartGmbB Stößlein Mertenbacher Gebelein, Nuremberg

Open spaces

Grosser-Seeger & Partner, Nuremberg

Opening of children’s and youth centre Pastoriusstraße