New construction After-school care centre Glogauer Straße

Project description

The three-group after-school care centre planned for the Glogauer Straße support centre is designed as a single, two-storey point building. The staircase is located in the centre of the new building. The new building is planned as a solid construction with a double-shell corrugated metal façade. The ceilings and walls therefore have load-bearing functions and the walls also consist of two layers. 
The new after-school centre fits in well with its surroundings outside the school grounds and its building line defines the continuation of the existing green space. Its two-storey construction and light, delicate façade cladding make it look like a pavilion within the green space.
The after-school care centre offers space for 60 children in 3 groups.

Location

The construction area for the new after-school care centre is located in the second row behind the support centre on Glogauer Straße on the grounds of the Greek school.

Energy standard

The project was planned on the basis of the “Guidelines for Energy-Efficient, Economical and Sustainable Building and Renovation”. EnEV standard will be implemented. This standard sets clear specifications for new buildings. 

Special features

The after-school care centre is planned to be barrier-free. Vertical access is provided by a centrally located lift. Corridors, doors and the associated movement areas are planned according to DIN specifications (specifications for barrier-free use). 
The after-school care centre has a disabled WC and electric motor-assisted entrance doors. In the probable event that a new school building is constructed and the outdoor nursery facilities currently located to the west have to be relocated to the north, the layout of the nursery and the building services have already been flexibly prepared for the relocation of the building’s exit to the outdoor nursery facilities.

Facts

Gross floor area

943 m²

Usable area

595 m²

Outdoor area

795 m² playground

Parking spaces

6 bicycle parking spaces

Total costs

Approx. €5.3 million

Start of construction

July 2020

Completion of construction

August 2022

Architects

Hering Architekten GmbH, Nuremberg

Open spaces

Führes Landschaftsarchitekten BDLA, Zirndorf

Building services

Ingenieurbüro Bautz, Ansbach

Statics

Trafektum GbR, Nuremberg

Building physics

Ingenieurbüro Seidel, Teublitz

Visualisation by Hering Architekten GmbH, Nuremberg