New construction NOW "Nord-Ost Wohnen"

Project description

106 new rental flats to be built at the Nordostbahnhof railway station

In February 2015, construction work began on 106 rental flats on the former railway wasteland at the Nordostbahnhof.
The project was realised in three construction phases. Five buildings were constructed in which, in addition to 66 privately financed rental flats, another 40 income-oriented subsidised rental flats, a day-care centre and an underground car park with 92 parking spaces were built.
The investment volume amounts to about €27 million, which includes subsidies for housing construction from the Free State of Bavaria for the rental flats subsidised by income-oriented subsidies. The entire complex was completed in autumn 2017.
The plans were drawn up by the architects at Aicher + Hautmann and Loebermann + Bandlow Architekten.

Facts

Residential units
   Subsidised
   Privately financed

106
  40
  66

Commercial units

    1

Parking spaces

  92 in the underground car park

Living space

7,995 m²

Commercial space

   737 m²

Total costs

€26.69 million

Start of construction

February 2015

Available

Construction phase A as of December 2017
Construction phase B as of April-May 2017
Construction phase C as of August 2017

Project management

wbg Nürnberg GmbH, Architektur & Städtebau, Gerd Bloß (construction phase A), Wolfgang Müller (construction phase B,C)

Architect

Architekturbüro Aicher + Hautmann, Nuremberg (construction phase A)
Loebermann + Bandlow, Nuremberg (construction phase B and C)

Technical building services planning

pbz Planungsbüro für Haustechnik ZEISIG GmbH & Co. KG, Birgland/Schwend

 

Structural planning

Dr. Kreutz+Partner Beratende Ingenieure, Nuremberg

 

Open spaces

Henschel, Landschaft + Design, Schnaittach

 

Building physics

CDM Smith Consult GmbH, Fürth

 

Nord-Ost-Wohnen district