In the series of modernisations of the core housing complex at the Nordostbahnhof railway station, the three existing buildings dating from 1955 with a total of 36 flats are being comprehensively modernised to make them more energy-efficient in 2023.
In addition to the energy measures of façade insulation, window renovation, the installation of basement ceiling insulation and the replacement of the heating system with a modern district heating system, the roofing is being replaced, the staircases and building entrances are being renovated and new balconies are being added to all flats.
The measures are rounded off with the restoration and partial redesign of the outdoor facilities.
The buildings are located in the north-eastern area of the Nordostbahnhof core housing complex. This area of the housing complex is not subject to ensemble protection.
After implementation of the measure, the buildings meet the KfW Efficiency House 100 standard. This means that the modernised house consumes 100% of the annual primary energy of a comparable new building. It thus meets the standard of a new building.
The measure is being carried out in an occupied building.
Residential units | 36 |
Living space | 2,043 m² |
Total costs | €3.4 million |
Start of construction | March 2023 |
Available | December 2023 |
Project management | wbg Nürnberg GmbH, Architektur & Städtebau, Mr Baudisch |
Architects | Ramstötter Dinkelmeyer Architekten GmbH, Nuremberg |
Technical building services planning | VIP Versorgungstechnik, Nuremberg |
Structural planning | Ingenieurbüro Schrittesser, Nuremberg |
Open spaces | Planungsbüro Kounovsky, Nuremberg |
Building physics | Ramstötter Dinkelmeyer Architekten GmbH, Nuremberg |